Target achieved
-
Target partially achieved*
-
Target missed*
-
Target in progress
*A new target will be formulated
| 2002/03 Targets | Progress | 2003/04 Targets | |
|---|---|---|---|
| 1. By March 2003, check that waste minimisation practices are continuing to be implemented at call centres. | Achieved. Waste minimisation practices implemented as part of normal business operations. |
![]() |
1. By March 2004, investigate methods of significantly reducing paper usage through the use of both electronic mailings and refinements to paper-based mailing campaigns. |
| 2. By March 2003, to measure the amount of waste from our Edinburgh Head Office with the aim of increasing the weight of items sent for recycling by at least 10%. | Achieved. Recycling weight has been increased by 10% during the year.
|
![]() |
2. By March 2004, reduce the amount of waste generated in the Edinburgh Head Office by 10% per colleague and raise the proportion of waste sent for recycling by 10% per colleague. |
| 3. By March 2003, to reduce the environmental impact of the Head Office through the implementation of the environmental action plan and to conduct regular audits to ensure 100% achievement. | Achieved Three audits conducted and continuing communications with colleagues on environment issues and the environment action plan. |
![]() |
3. March 2004, review the implementation of the Edinburgh Head Office Environmental Action Plan with a view to further reducing its environmental impact and set quantified targets. |
© J Sainsbury plc 2003